Best Cable Mfg

Request for quote

What to send with a cable assembly or wire harness RFQ

Quotes are only comparable if every supplier is pricing the same part. This checklist closes the gaps suppliers otherwise fill with assumptions.

The package

Definition of the part

Workmanship and test

Identification and delivery

Commercial and compliance

Package by part type

If you are buyingMake sure the package also covers
A point-to-point cable assemblyCable specification (jacket, shielding, temperature), overall length and tolerance, strain relief or overmold, sealing rating
A branched wire harnessLayout drawing with breakouts, branch lengths, bundling and protection by zone, connector clocking, label positions
An overmolded assemblyMold geometry, compound, color, markings, and who owns the mold. See overmolded cable assemblies.
Aerospace or defense partsAS9102 FAI, quality clauses, counterfeit-part controls, export marking, source inspection
Automotive partsPPAP level, crimp and connector performance specifications, customer-specific requirements

The drawing itself carries most of this. See what to put on a wire harness drawing for the notes most often missed.

Ask for these back in the quote

Ask every supplier to state the following in their quote, so that you compare like with like:

  1. Piece price at each quantity break, with tooling and NRE listed separately.
  2. Lead time for the first article and for production, and the longest-lead component that drives it.
  3. Any exceptions or assumptions they made about your package, and any parts they propose to substitute.
  4. How long the quote is valid, especially where connector or metal prices are volatile.

Why the exceptions list matters most. The cheapest quote often carries an exception that removes a test or swaps a connector. Reading the exceptions first can save you from comparing an apple with a cheaper, different apple.

Not sure yet whether you are buying a cable assembly or a harness? Read the difference. It changes how suppliers quote the part.

Common RFQ mistakes

After the quotes come back

  1. Read the exceptions first and resolve each one, in writing, with the supplier.
  2. Normalize the quotes: same quantities, tooling separated, same documentation.
  3. Check the lead-time driver each supplier named, and whether they agree.
  4. Compare total cost, including tooling amortized over your expected volume, freight and the cost of your own inspection effort.
  5. Verify the finalists against their certification records before awarding. See how to verify supplier certifications.

Common questions

How many suppliers should get the RFQ?

Enough to compare, few enough to review properly. Many buyers send to three to five qualified or pre-screened suppliers. Send each one the same package, and the same answers to questions.

Should I send an RFQ before the drawing is final?

A budgetary quote on a draft is useful for planning. Mark it as preliminary, and re-quote on the released revision before ordering.

Can I send export-controlled drawings with an RFQ?

Only to suppliers able to receive them under the applicable regulations. Check with your export compliance team before sending, and mark the data correctly.

What is a reasonable quote validity?

It depends on how volatile your components and metal prices are. Ask each supplier to state it, and to say which items are most exposed to price changes, so you know what to re-check before ordering.

Why do quotes for the same part differ so much?

Usually because of different assumptions about class, tests, documentation, component sources and tooling. See what drives the cost of a custom wire harness.

Last reviewed 2026-09-17